Current works

The Hull Heat Network is currently under construction, with works underway on both the Energy Centre and pipe network

The network will include the installation of between 2 and 4 pipes, creating a flow-and-return system that will distribute hot water from the Energy Centre to connected buildings to provide heating and hot water.

Initially, the Energy Centre will heat the water using a combination of air source and water source heat pumps. Work is also ongoing to secure suppliers of waste heat to decrease carbon emissions. To minimise disruption for road users and pedestrians, Hull Heat Network construction works are being coordinated with other city centre projects.

Project updates

The Energy Centre

Construction of the Energy Centre, located on the former Trippett Street Car Park, is progressing well.

The flue and thermal stores are due to be delivered at the end of July.

Once completed, the Energy Centre is expected to be operational by mid-2027.

Current works

The next phasing of the Network installation is currently ongoing in collaboration with other schemes in the City Centre.

Planned works

To be confirmed

  • Albion Street
  • Alfred Gelder Street/Queens Dock Avenue between Guildhall Road and Carr Lane
  • Anne Street
  • Bond Street
  • Carr Lane
  • Clarence Street
  • George Street crossing to Charlotte Street Mews
  • High Street
  • Lowgate
Completed works
  • Alfred Gelder Street
  • Charlotte Street Mews
  • Gandhi Way
  • George Street crossing to Charlotte Street
  • Guildhall Road
  • Hannover Square
  • Jarrett Street
  • Quay Street
  • Worship Street

If you have a question, you may find the answer on our frequently asked questions.